| Main Contractor: |
|
Allen Build |
| Site: |
|
Grays Inn Road , Clerkenwell, London |
| Description: |
|
104 Apartments |
| Works Undertaken: |
|
MS partitioning, MF suspended ceilings, Gyvlon Screeding |
| Contract Value: |
|
£0.5 million |
| Duration: |
|
36 Weeks - Current |
| Main Contractor: |
|
Mansell |
| Site: |
|
Blue Hut, Nile Street , London , N1 |
| Description: |
|
175 Apartments and Youth Club Area |
| Works Undertaken: |
|
Fire protection, MS partitioning and MF suspended ceilings, Screeding |
| Contract Value: |
|
£1.6 Million |
| Duration: |
|
35 Weeks – Current |
| Main Contractor: |
|
St George Central London Limited |
| Site: |
|
Imperial Wharf , Block C21 1-3, Townmead Road,
Fulham, London SW6 |
| Description: |
|
151 Luxury Apartments |
| Works Undertaken: |
|
MS partitioning, MF suspended ceilings and drylining |
| Contract Value: |
|
£2.2 million |
| Duration: |
|
September 2004 – August 2005 |